Frustration at year-long wait to switch on 500 solar panels | Bradford Telegraph and Argus

2023-02-15 18:40:53 By : Mr. Dongfang Yin

CRAVEN District Council is still waiting to switch on 528 solar panels at Craven Leisure in Skipton — over a year after they were installed.

The solar panels were placed on the roof of the leisure centre in Aireville Park in November 2021 as part of a £1.2m project to reduce carbon emissions at the council’s buildings. Remote Control Air Source Heat Pump

Frustration at year-long wait to switch on 500 solar panels | Bradford Telegraph and Argus

But the council says it is still awaiting confirmation from energy distributor Northern Powergrid before they can be used, meaning the solar panels have not generated a single electron of renewable energy.

An air source heat pump that was installed in 2022 to heat the swimming pool has also not been turned on.

Over the last year, the price of energy has rocketed. A recent council meeting heard how gas and electric bills at Craven Leisure have increased by 124 per cent.

David Noland, Green Party councillor for Skipton North, told the Local Democracy Reporting Service he is frustrated by the delay.

He said: “They are sat in place so it’s a huge problem for the council. Swimming pools are very expensive to run and these solar panels will go a long way to cutting carbon emissions. Everybody is frustrated at the delay — from the councillors who voted for the project to the officers who have done the hard work.”

A report published last month revealed the authority is set to spend an extra £631,000 on energy bills at its buildings, including Craven Leisure, which is one of its largest.

Chairman of Craven District Council, Simon Myers, said the council has written to government ministers and Prime Minister Rishi Sunak regarding support for energy bills at the leisure centre.

A spokesperson for Craven District Council admitted the authority does not know when the solar panels will be turned on.

The spokesperson said:“Craven Leisure is among the most significant buildings in Craven District Council’s estate to get renewable energy systems retrofitted in the past couple of years.

“Craven Leisure centre’s energy usage is high due to nature of the facility and services provided.  In 2021, the leisure centre saw the installation of 528 solar panels as part of the council’s £1.2m Zero Carbon Craven project. The delay is caused by a third party, we are yet to receive a firm date for the final stages of the project.

“Council officers are proactive and reached out to all parties involved, but we cannot continue without the confirmation from Northern Powergrid. We will endeavour to complete this project as soon as we can.”

A spokesperson for Northern Powergrid said: “We cannot comment on an individual customer’s connection request due the commercial nature of these requests. Delivering a new network connection involves a range of steps from design and planning to delivery. In many cases, this can also require securing access and agreement to work on other people’s land to enable the connection. Throughout the process our team keeps our customers updated on any situations where agreement with other parties is required and the status of it.

“Work can only start once all the necessary permissions are in place. Our wayleave team seeks to secure these for our customers as soon as possible. Customers are also able to directly approach any third-party landowners to discuss or secure a direct agreement that can help enable their connection, should they wish to do so.”

We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.

Please report any comments that break our rules.

Are you sure you want to delete this comment?

This website and associated newspapers adhere to the Independent Press Standards Organisation's Editors' Code of Practice. If you have a complaint about the editorial content which relates to inaccuracy or intrusion, then please contact the editor here. If you are dissatisfied with the response provided you can contact IPSO here

© 2001-2023. This site is part of Newsquest's audited local newspaper network. A Gannett Company. Newsquest Media Group Ltd, Loudwater Mill, Station Road, High Wycombe, Buckinghamshire. HP10 9TY. Registered in England & Wales | 01676637 |

Data returned from the Piano 'meterActive/meterExpired' callback event.

As a subscriber, you are shown 80% less display advertising when reading our articles.

Those ads you do see are predominantly from local businesses promoting local services.

These adverts enable local businesses to get in front of their target audience – the local community.

Frustration at year-long wait to switch on 500 solar panels | Bradford Telegraph and Argus

Air Source Heat Pump With Radiators It is important that we continue to promote these adverts as our local businesses need as much support as possible during these challenging times.